A Landmark Achievement: Building India’s Largest E-Commerce Fulfillment Center for Amazon
In March 2024, the Skymettle office buzzed with excitement
as the team celebrated a historic milestone—the signing of the Agreement to
Lease with Amazon India. After months of relentless effort, Skymettle
Infrastructure had secured the contract to develop what would become India’s
largest e-commerce fulfillment center.
This wasn’t just another project; it was a defining moment
for Skymettle. The challenge? Constructing a massive 430,000 sqft warehouse on
a 22-acre land parcel, with Amazon’s stringent requirements setting the bar
higher than ever before. For Skymettle, this was an opportunity to prove its
capabilities in large-scale Industrial
Spaces Developers in India.
The Challenge: Building at an Unprecedented Scale
Amazon’s vision was clear—a state-of-the-art fulfillment
center that would serve as the backbone of its supply chain in India. The
facility had to be designed for seamless operations, with durability, safety,
and efficiency as top priorities.
Key requirements included:
- Heavy-Duty
Flooring – Capable of withstanding 50 years of constant use.
- Advanced
Fire Safety Systems – Ensuring the safety of over 2,400 workers
at any given time.
- Climate-Controlled
Environment – Temperature regulation across the massive
structure.
- Robust
Infrastructure – Roads designed to handle 200+ truck movements
daily.
Engineering Excellence: The Numbers Behind the Project
The sheer scale of construction was staggering. Some of the
standout features included:
✔ 35 Rainwater Harvesting Units –
Utilizing Japanese technology for sustainability.
✔ Solar-Powered Operations –
50% of the roof covered with solar panels.
✔ 28.57 km of Firefighting
Systems – Compliant with international FM Global standards.
✔ 4,550 MT of Steel &
25,000 cum of Concrete – Reinforcing the structure for longevity.
✔ TR34-4th Edition FM-2
Flooring – Ensuring durability under heavy loads.
✔ Seamless, Insulated PEB
Structure – Optimizing energy efficiency.
Speed Without Compromise: Delivering Ahead of Schedule
With a tight deadline, Skymettle mobilized a workforce of
1,000 professionals. Construction began on June 21, 2024, and
by December 20, 2024, Amazon was able to start fit-outs. The
facility was fully operational by May 31, 2025—a testament to
Skymettle’s execution prowess.
A Testament to Teamwork & Vision
Looking back, this project wasn’t just about constructing a
warehouse; it was about pushing boundaries. The success reinforced a core
belief—when a committed team comes together, even the most ambitious goals
are achievable.
Skymettle is proud to have partnered with Amazon on this
landmark project. The experience has positioned us as leaders in industrial and warehousing development,
ready to take on the next wave of infrastructure demands in India.
Interested in learning more about our capabilities?
Reach out to us at infra@dfplgroup.com—we’d love to collaborate on your
next big project!